Resolved
Management switch has been replaced.
CPU Rack01 fully is now operational again.
Investigating
Management switch failing will be replaced today (Thursday, September 10 2026).
Rack01 was reserved for the duration of the maintenance to avoid impacts on user jobs.
Investigating
CPU rack01 is partially operational.
24 CPU nodes remains unavailable, management hardware will be replaced in the coming days.
Investigating
Dear MeluXina users,
During some maintenance work in the datacenter, Rack01 (CPU nodes) lost power.
This power loss induced reboot of 96 CPU compute nodes.
The issue is currently being investigated.
For any questions, please contact our Service Desk.
Thank you for your understanding
The LuxProvide team